NEW QUESTION 18
(In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)

 
 
 

NEW QUESTION 19
(Which two answers show characteristics of Test on Completion or Test After Completion under the FIDIC Silver Book (edition 1999)?
Choose all of the correct answers (multiple possibilities).)

 
 
 
 

NEW QUESTION 20
Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NEW QUESTION 21
You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project ‘ s design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

 
 
 
 

NEW QUESTION 22
Which one of the following claim events does NOT allow profit?

 
 
 
 
 

NEW QUESTION 23
(Under the FIDIC Yellow Book (edition 1999), any delay caused by Authorities will be considered as a cause of Delay under sub paragraph (b) of Sub-Clause 8.5 under the only condition that the Contractor has diligently followed the procedures laid down by the public authorities in the Country. Is this statement true or false?)

 
 

NEW QUESTION 24
You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999).
There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter?

 
 
 
 

NEW QUESTION 25
In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an “ad-hoc” basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)

 
 
 
 

NEW QUESTION 26
(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)

 
 
 
 

NEW QUESTION 27
(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)

 
 
 
 

NEW QUESTION 28
Which two statements reflect an INCORRECT application of a Golden Principle?

 
 
 
 

NEW QUESTION 29
You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?

 
 
 
 

NEW QUESTION 30
(Golden Principle 2 states that ” The Particular Conditions must be drafted clearly and unambiguously. ” Which statement best underlines this Golden Principle in relation to the FIDIC Red, Yellow, and Silver Books (both editions)?)

 
 
 
 

NEW QUESTION 31
Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ‘ s Requirements. Which statement is correct?

 
 
 
 

NEW QUESTION 32
(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)

 
 
 
 

NEW QUESTION 33
(You are the Contract Manager of the Employer ‘ s Representative in a Thermal Power Plant Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims:
(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer’s Requirements.
(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated).
What is your determination for the Contractor?)

 
 
 
 

NEW QUESTION 34
Which of the following documents form part of a FIDIC Construction Contract [“Red Book” (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).

 
 
 
 
 

NEW QUESTION 35
Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NEW QUESTION 36
(Which two statements are correct for the FIDIC Red Book (edition 2017)?
Choose all of the correct answers (multiple possibilities).)

 
 
 
 

NEW QUESTION 37
Which one statement regarding the adjustment of the Contract Price as mentioned in Sub-Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?

 
 
 
 

NEW QUESTION 38
FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

 
 

NEW QUESTION 39
You are the Contract Manager of the Contractor in a building project. The Contract has been awarded to your firm, but the Engineer has not been selected. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, which must be done within 14 days after the signing of the Contract Agreement. The Employer requested your firm to commence works on the 14th day after signing the Contract Agreement. Your director, Y, wants to wait with commencing the works until the Engineer has been selected or until the 42 days since the date your firm receives Letter of Acceptance. Is Y correct?

 
 

NEW QUESTION 40
(Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)

 
 

NEW QUESTION 41
You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project’s design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

 
 
 
 

NEW QUESTION 42
Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

 
 

CCM Certification All-in-One Exam Guide Sep-2026: https://www.actualtorrent.com/CCM-questions-answers.html

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt www.stes.tyc.edu.tw www.stes.tyc.edu.tw myportal.utt.edu.tt