The AACE-PSP Exam consists of 120 multiple-choice questions that cover a range of topics related to project planning and scheduling. These topics include project scheduling concepts, time management techniques, critical path method (CPM) analysis, and earned value management (EVM). AACE-PSP exam also covers risk management concepts, including risk identification, analysis, and mitigation. Candidates must complete the exam within four hours and achieve a passing score of 70% or higher to earn the AACE-PSP certification.

 

NEW QUESTION 30
What method offers the best chance of the schedule being used effectively to implement the project in the field?

 
 
 
 

NEW QUESTION 31
You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company’s board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule’s work activity durations?

 
 
 
 

NEW QUESTION 32
The amount of time that an activity can be delayed from its early start date without delaying project completion is called

 
 
 
 

NEW QUESTION 33
Budgeted cost of work scheduled is _______________________.

 
 
 
 

NEW QUESTION 34
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

 
 
 
 

NEW QUESTION 35
Why does activity 11001 not show successor activities?

 
 
 
 

NEW QUESTION 36
Which statement is true?

 
 
 
 

NEW QUESTION 37
Which is NOT an industry-recognized methodology for quantifying critical delay?

 
 
 
 

NEW QUESTION 38
An earned value-based project control system can use either of which two budgets as the basis of its calculations?

 
 
 
 

NEW QUESTION 39
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the “normal” schedule would be affected?

 
 
 
 

NEW QUESTION 40
Determine the correct formula and date for the late finish for Activity 9004.

 
 
 
 

NEW QUESTION 41
Which of the following is NOT input data to the construction planning process?

 
 
 
 

NEW QUESTION 42
Which activity is drawn in the incorrect position?

 
 
 
 

NEW QUESTION 43
Resource planning must take all of the following into account except for

 
 
 
 

NEW QUESTION 44
Activity C is a

 
 
 
 

NEW QUESTION 45
What problems can a soils engineer deal with on a project?

 
 
 
 

NEW QUESTION 46
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing “no differing sit conditions” and “no damage for delay” clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
“normal” schedule and $3,200 for the “crashed” schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor’s operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the “normal” schedule, what is the cost of this hammock?

 
 
 
 

NEW QUESTION 47
Identify the late finish to develop plans and specs.

 
 
 
 

NEW QUESTION 48
Determine the correct formula and date for the late finish for Activity 2002.

 
 
 
 

NEW QUESTION 49
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

 
 
 
 

NEW QUESTION 50
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

 
 
 
 

NEW QUESTION 51
Project delays are best analyzed

 
 
 
 

NEW QUESTION 52
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

 
 
 
 

NEW QUESTION 53
Using the “normal” schedule, what is the early finish date of activity 10002 and its total float?

 
 
 
 

Introduction to Planning & Scheduling Professional (PSP) Exam

A PSP is a technical specialist in planning and scheduling with specialized experience in project planning and the production, tracking, updating, forecasting, and analysis of integrated project schedules. Under the AACE International Total Cost Management (TCM) system, the PSP leads the planning and scheduling process. A PSP can interact efficiently, both internal and external, with all project stakeholders.

In each of those chapters, the PSP Certification exam is divided into two main chapters (Planning and Scheduling) and two sections. A glimpse of all these sections could be found in the PSP exam dumps as well:

  • Planning development
  • Schedule development
  • Planning product
  • Schedule maintenance and reporting

Planning is the mechanism by which the length of the project task is added to the schedule is to define the project goals and the orderly tasks required to complete the project (the thought part) and not to be confused with scheduling.

Scheduling is a summary of when it is possible to complete each operation in a project and
It must be finished to be done on schedule. The simplest of schedules displays the beginning and completion of operations of a given period in bar chart format. More complex schedules provide schedule logic, usually in CPM format, and display the critical path and floats associated with each operation. A time series of events and activities that reflect an operational timetable. The schedule describes the relative task start and end times and event occurrence times. On a calendar framework or on an elapsed time scale, a schedule can be presented.

The exam is administered through computer-based testing (CBT) and consists of questions of multiple choice and essay-style questions. This test is a closed book. Programmable or preprogrammed calculators are also allowed (including those with financial functions). See the PSP practice exams to understand the paper format. This exam provides a framework for formally evaluating the expertise and abilities of the person in a subject against generally agreed standards. It recognizes those who have
demonstrated their experience and expertise in planning and scheduling.

AACE International is a globally recognized professional association for cost engineering, project management, and planning and scheduling professionals. AACE International offers various certification programs to recognize professionals’ expertise in different areas. AACE-PSP (Planning & Scheduling Professional) is one of the certification programs that AACE International offers.

 

AACE-PSP 2024 Training With 120 QA’s: https://www.actualtorrent.com/AACE-PSP-questions-answers.html

Related Links: www.stes.tyc.edu.tw myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Be the first to reply

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below