QUESTION 53
Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of
01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)

 
 
 
 

QUESTION 54
Where should you specify the Default Capitalized Interest Rate Schedule?

 
 
 
 
 

QUESTION 55
In a Project Draft Invoice preview, quantity (hours) and unit price (bill rate) are shown as fields on the invoice. Quantity and unit price are then used to calculate the line total, then the total price of the invoice.
After the invoice is transferred or created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)

 
 
 
 

QUESTION 56
Your client has decided to import time cards into Project Costing from Oracle Fusion Time and Labor. They have a requirement to make adjustments to time card entries whenever needed.
In which work area will the employees and contingent workers be able to modify their time cards?

 
 
 
 

QUESTION 57
Which five steps are required for the File-Based Data Import Integration option?

 
 
 
 
 
 
 

QUESTION 58
Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)

 
 
 
 
 

QUESTION 59
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)

 
 
 
 
 

QUESTION 60
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)

 
 
 
 

QUESTION 61
Which step within the functional setup manager helps you to move your verified setup data from the test environment to a production environment?

 
 
 
 
 

QUESTION 62
Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a 10 spread point scale resembles:
0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. ( Choose two)

 
 
 
 

QUESTION 63
Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)

 
 
 
 

QUESTION 64
You search for resources to fulfill a project resource request but are unable to proceed after receiving the following error message: “The search for resources cannot be completed because the project resource search index is not available. Contact your help desk.” Identify the cause for this error message. (Choose the best answer.)

 
 
 
 

QUESTION 65
Which two statements describe how the Resource Qualification Score is calculated?

 
 
 
 

QUESTION 66
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X – Task 10, and Bill Plan B is allocated against Project Y – Task 30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)

 
 
 
 

QUESTION 67
Which product offering simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud?

 
 
 
 

QUESTION 68
Stigma Consulting wants to implement the program management capability to coordinate and track their strategic programs.
Which three components are required to configure the program options as part of implementing the program management capability? (Choose three.)

 
 
 
 
 

QUESTION 69
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)

 
 
 
 

QUESTION 70
Which setup option is common to both financial and project plan types?

 
 
 
 

QUESTION 71
Which application would you use to map application roles to external roles? (Choose the best answer.)

 
 
 
 

QUESTION 72
Stigma consulting has been hired by a client to implement Project Management Cloud. Which role should they assign to a user for using the rapid implementation feature to set up the Project Financial Management offering by populating and uploading a Microsoft Excel workbook?

 
 
 
 

QUESTION 73
Which product offering enables non-exclusive relationships between multiple projects and tasks with contracts and contract lines? (Choose the best answer.)

 
 
 
 

Oracle 1z0-1057-25 Real 2026 Braindumps Mock Exam Dumps: https://www.actualtorrent.com/1z0-1057-25-questions-answers.html

Related Links: www.stes.tyc.edu.tw www.stes.tyc.edu.tw myportal.utt.edu.tt myportal.utt.edu.tt github.com myportal.utt.edu.tt

Be the first to reply

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below